More news on this day
Los Angeles’ long-awaited automated people mover at LAX is unlikely to be ready for the 2026 FIFA World Cup, after years of schedule slippage, contract disputes and cost overruns on the multibillion-dollar project meant to unclog one of the world’s busiest airport roadways.
Get the latest news straight to your inbox!

A Train Meant for 2023 Slips Past the World Cup
The 2.25-mile elevated train, officially branded SkyLink, is the centerpiece of Los Angeles World Airports’ Landside Access Modernization Program, a broader package that also includes new parking, transit hubs and a consolidated rental car facility. Construction on the line began in 2019 with an initial opening target of 2023, positioned as a signature upgrade ahead of a decade of mega-events including the World Cup in 2026 and the Olympic Games in 2028.
Publicly available timelines show that the opening date has since moved several times, from 2023 to early 2026 and then to the second half of 2026. Local coverage in recent months has described the people mover as “unlikely to be fully operational” in time for next summer’s World Cup, even as Los Angeles prepares to host multiple matches starting in June 2026. Project updates now refer to a late-2026 launch window, leaving a gap between the arrival of global crowds and the debut of the rail link intended to carry many of them.
In the meantime, reports indicate that the system has entered intensive testing. Coverage in April and May described trains running on a full simulated schedule without passengers, part of a multiweek demonstration phase required before regulators can clear the line for public service. The elevated guideway and stations appear largely complete, but the testing period, safety sign-offs and remaining integration work leave little margin before World Cup kickoff.
The shifting timeline underscores how difficult it has been to deliver what, on paper, is a relatively short airport circulator. Instead of being the polished showpiece greeting visitors during the tournament, the people mover risks becoming a case study in how complex contracting structures, utility coordination and change orders can derail even high-profile mobility projects.
Rising Price Tag and High-Stakes Settlements
Alongside schedule setbacks, the cost of the LAX people mover has climbed sharply. The train is part of a larger access program frequently described as a 5.5 billion dollar effort, but separate reviews have focused specifically on the automated system’s overruns. A 2024 county civil grand jury report, summarized in later policy research, cited roughly 880 million dollars in cost growth on the people mover alone compared with earlier estimates.
City records and local reporting show that since 2021, the airport’s governing board has approved a series of amendments and settlements with the project’s private consortium, LAX Integrated Express Solutions. These actions have added hundreds of millions of dollars for claims tied to delays, design changes and integration issues. One previous decision in 2024 followed a technical expert’s finding that Los Angeles World Airports bore responsibility for hundreds of days of delay related to power, communications and interface work with other projects.
More recent documents before the Los Angeles City Council in July 2026 describe a new settlement agreement intended to resolve a fresh round of claims under the long-term contract that covers design, construction, operations and maintenance. The series of financial adjustments has pushed the combined cost of the people mover portion into the range of 3.3 billion dollars, according to recent broadcast coverage, well above the price tag often cited when the project was first announced.
The funding structure adds political sensitivity. The project uses airport revenues and private financing rather than local sales taxes, but it sits at the center of regional debates about whether Los Angeles can deliver major infrastructure on time and on budget. With the World Cup and Olympics both on the horizon, the overruns and payouts are drawing renewed scrutiny from city leaders and watchdogs.
Disputes, Utilities and the Anatomy of Delay
Publicly available information and local coverage point to a complex mix of factors behind the repeated delays. One major theme has been the relationship between Los Angeles World Airports and the LINXS consortium. Over several years, the two sides have traded claims over responsibility for schedule impacts, with disputes revolving around site access, power supply, integration with airport communications and coordination with the separate Metro transit hub project.
A 2024 arbitration ruling found that the airport agency contributed significantly to delay by not providing timely integration with communications systems and by complications connected to the Metro station. At the same time, subsequent negotiations have involved claims from both the agency and the contractor, leading to a chain of settlements rather than a single resolution. Local analyses describe this as a “contractor versus owner” standoff that has spilled into public view via board items, council files and grand jury findings.
Another challenge has been utility work and permitting. Reports from 2025 and 2026 describe extended power shutoffs that slowed testing of key systems, as well as follow-on work involving landscaping, pavement repairs and fire safety infrastructure. Even as the physical guideway reached more than 99 percent completion, relatively small but critical elements such as sprinkler connections and inspection approvals became flashpoints in the schedule.
Observers note that the people mover’s public-private structure, with a long operating concession attached to construction, may have amplified the stakes of each delay claim. Because the contractor is expected to operate and maintain the system for decades, disputes over long-term risk allocation and maintenance standards influenced negotiations about what needed to be finished, who was responsible for changes and when penalties or relief events applied.
World Cup Transport Plans Pivot Back to Buses
The World Cup spotlight is intensifying questions about how fans will actually reach LAX and nearby stadiums without the people mover in service. The tournament’s first Los Angeles-area match is scheduled for June 2026, a point at which current projections only tentatively suggest that testing could be wrapping up. As a result, contingency planning has shifted toward beefed-up shuttle bus operations and wayfinding improvements in the existing terminal roadways.
Airport planning documents released in late 2025 and early 2026 include contract extensions for shuttle providers, explicitly allowing services to continue if the automated system is not yet open. These filings describe a desire to maintain flexibility so that high-capacity buses can keep running between parking, the new intermodal facility and terminals, even beyond original end dates tied to a now-superseded opening forecast for the people mover.
City transportation planners and regional transit agencies are also revisiting how spectators will move between the airport, downtown Los Angeles and venues like SoFi Stadium. Without the direct rail link to the Metro network, tournament visitors are more likely to rely on a combination of shuttle buses, existing light rail lines, ride-hailing vehicles and private coaches. That mix increases pressure on already congested road corridors around LAX and could dampen some of the environmental benefits originally promised by the automated train.
Travel industry observers suggest that, for many visitors, the absence of the people mover may be most visible in missed expectations. Promotional materials over the past decade have frequently showcased renderings of sleek trains gliding above traffic, framing the system as a symbol of a more transit-oriented Los Angeles. With that vision now arriving after the World Cup rather than before it, the city will be leaning on more traditional solutions at precisely the moment it hoped to unveil a modern gateway.
Legacy Questions Ahead of the 2028 Olympics
Even as attention focuses on the World Cup, the people mover’s ultimate test will likely come with the 2028 Summer Olympics. Regional planners still expect the system to be fully operational well before that event, alongside a host of other rail extensions and airport upgrades. The hope is that, by then, memories of construction delays and contract fights will fade as passengers enjoy quick, predictable transfers between rail, rental cars, parking and terminals.
For now, though, the project’s troubled path is shaping broader conversations about risk-sharing on major public works. Analysts and advocacy groups are using the LAX experience to question whether complex public-private partnership structures have delivered on promises of on-time, on-budget delivery. Others argue that the alternative of purely public procurement has its own challenges and that lessons from the people mover can still inform future deals.
Meanwhile, construction and testing continue under intense public scrutiny. Each new status report, council file and media update is parsed for hints of further slippage or signs that the late-2026 window is firming up. As the World Cup countdown clock ticks, Los Angeles is confronting a paradox familiar to many global cities: the same international events that inspired ambitious infrastructure plans are now exposing, in real time, how difficult they can be to complete.