Missoula is moving from planning to action on a long-discussed sixth fire station, with recent budget decisions and design work outlining how the growing city intends to expand fire coverage and keep pace with rising emergency calls.
Get the latest news straight to your inbox!

New station tied to growth, response time concerns
Publicly available city budget documents describe Fire Station 6 as a priority public safety project intended to improve response times in fast-growing parts of Missoula. City materials note that annexations and continued residential and commercial development have stretched existing fire coverage, pushing some neighborhoods beyond national benchmarks for how quickly crews should arrive at emergencies.
Analysis summarized in the city’s capital planning paperwork indicates that emergency call volumes have climbed steadily in recent years, while the number and location of Missoula’s existing stations have remained largely unchanged. The planned sixth station is framed as a way to relieve pressure on current crews and reduce the number of calls where response times fall outside recommended standards.
According to the city’s Community Investment Program forms, the project is categorized as “urgent” within the fire department’s long-range planning. The documentation links the station directly to the department’s master plan, the city’s broader growth strategy and goals around equitable access to emergency services.
Design work underway as city sets project timeline
Recent City Council agenda materials show that Missoula has authorized funding to move ahead with design for Fire Station 6. A design contract adopted earlier this year sets a not-to-exceed amount and outlines a schedule to bring the station from concept into detailed architectural and engineering plans.
The design phase is expected to refine the building’s layout, apparatus bay configuration and living quarters for firefighters, as well as site circulation for emergency vehicles and public access. Planning documents indicate that a third-party study on fire station siting has been used to help determine the most effective general area for the project based on travel times and projected demand.
City budget narratives describe the station as the future permanent home for a sixth engine company that has already been added to the department’s staffing plan. For now, that crew is operating from existing facilities, with the intent that it will relocate once Station 6 is built and equipped.
Voter-approved levy and impact fees anchor funding plan
Financing for Fire Station 6 draws from multiple sources that city records trace back several budget cycles. A voter-approved fire levy, passed in recent years, is identified in public coverage as a key mechanism that allowed Missoula to hire additional firefighters and begin planning for the new station.
Capital program documents break out projected costs for land, construction, site improvements and equipment. The forms list several million dollars in anticipated spending in the 2026 fiscal year, including funds earmarked for property acquisition, building construction and interior and exterior improvements. Smaller allocations are set aside for station furnishings, specialized equipment and required public art contributions under city policy.
Impact fees collected from new development are also included in the funding mix. According to the city’s capital planning tables, these fees are being applied to help cover one-time bricks-and-mortar costs, reflecting the connection between new growth on the urban fringe and the need for expanded fire coverage.
Location study and land acquisition guide siting
While early documents referred to a third-party siting study to pinpoint the optimal location for Fire Station 6, more recent city bid notices indicate that Missoula is now actively considering property acquisition for the project. A posting on the city’s procurement page describes plans to secure a site and proceed with construction for the new station.
The location process is being shaped by several factors commonly cited in urban fire planning, including how quickly engines can reach new subdivisions, freeway corridors and commercial areas. Publicly available materials reference the use of travel-time modeling and service coverage analysis to help ensure that Station 6 fills existing gaps rather than duplicating coverage already provided by the current network of stations.
City forms also highlight the need to coordinate with nearby transportation and utility projects so that access roads, sidewalks and essential services are in place by the time construction begins. This coordination is portrayed as important both for day-to-day operations and for maintaining safe, efficient routes for fire engines during emergencies.
Construction aligned with Missoula’s 2026 budget
The city’s adopted Fiscal Year 2026 budget identifies the start of construction on Fire Station 6 as one of several major infrastructure initiatives scheduled in the coming cycle. Budget summaries characterize the station as a voter-backed project that will move from the drawing board into site work and building activity during the 2026 fiscal year.
Missoula’s capital planning tables assign high completion percentages to preliminary phases of the project, such as land and core building planning, suggesting that much of the groundwork has been laid ahead of physical construction. Additional line items for improvements and equipment indicate that the city expects to continue investing in the station across multiple years as the structure is finished and brought into service.
For residents, the most visible signs of progress are likely to appear as site acquisition, design milestones and contractor selections are finalized. According to budget and procurement records, city leaders have laid out a path that moves Fire Station 6 from long-term concept to a funded, scheduled project, signaling a significant expansion of Missoula’s fire protection network in the years ahead.